Long Giang Cooperates With Deo Ca Joint Venture To Construct Line Connecting Long Thanh Airport
Long Giang Cooperates With Deo Ca Joint Venture To Construct Line Connecting Long Thanh Airport Long Giang Cooperates With Deo Ca Joint Venture To Construct Line Connecting Long Thanh Airport

Long Giang Cooperates With Deo Ca Joint Venture To Construct Line Connecting Long Thanh Airport

These two routes belong to package number 6.12 – Component project 3: Essential works in the airport under the Long Thanh International Airport construction investment project phase 1.

The total length of the two routes is 7.8km with a value of 2,630 billion VND, implementation time is 885 days from the date of commencement. The start of construction of two routes has a particularly important meaning, marking the opening of a large construction site with many items being implemented simultaneously with items at the Long Thanh International Airport Construction project.

Package 6.12 was implemented by a consortium of 6 contractors led by Deo Ca Group. Long Giang Company has been trusted by Deo Ca Group to sign a contract to construct 350 bored piles of Super T bridge – intersection of line 1 – line 2 and intersection bridge of line 2 – Ho Chi Minh – Long Thanh expressway.

Long Thanh International Airport is an important gateway, aiming to become an international and regional transit center. This is an important project with great significance in the country’s socio-economic development process. Building a transportation system connecting Long Thanh airport with key traffic routes is very important, improving passenger accessibility, contributing to exploiting the maximum potential and advantages of the National Airport. Long Thanh temple.

Recognizing the importance of the bidding package, the Group and the contractors in the joint venture have determined to prioritize the best resources for the bidding package, ensuring that the bidding package is delivered on time.

Sharing the same goal as the contractors participating in the construction of the project and especially the first construction phase of the package, Long Giang Contractor proactively prepared adequate personnel, machinery and equipment to ensure both in terms of quantity, quality as well as detailed material supply plans ready to deploy the bidding package immediately after the groundbreaking ceremony with the criteria: “SAFETY – QUALITY – PROGRESS”.

Currently, the Steering Committee of Long Giang Foundation is focusing resources and planning to implement construction work for the project to ensure the delivery of high quality, safe and on-schedule items. committed.